Kimberly Court Trail Paving
Kimberly Court Trail Paving
Anticipated Timeline: Construction August 2021Project Description: The Kimberly Court Trail Paving project includes removal of existing driveway culverts, installing storm sewer, filling of existing ditches, and grading and paving of a new 10’ asphalt trail. Completion of the project will provide off-street pedestrian accommodations for a safer route and a connection of the existing trail system to the school.
Project Updates:
- August 10, 2021 - Update
- Week of 8/23/2021: Pavement removal and rough grading of base aggregate and topsoil.
- Week of 8/30/2021: Final grading of base aggregate and potentially pave depending on weather.
- Week of 9/6/21: Fine grading of trail.
- Week of 9/13/21: Asphalt paving and restoration.